positive OCCTO measured output on 2026-11-08 · not live
Every reactor.
One evidence layer.
Operating snapshots, restart candidates, construction, decommissioning, legacy plans and active site studies—kept in distinct evidence categories.
72 entries combine separate portfolios: 33 existing commercial reactors, 27 JAIF closed-down entries, 3 under-construction units, 8 legacy planned units and 1 site study. This is a map coverage total—not a fleet denominator.
existing reactors, not operating claims
separate JAIF UC table
plus 1 fully decommissioned entry
Mihama successor · no design decision
JAIF PL table · no build dates
Filter the national reactor landscape
The default view shows every tracked layer. Turn categories on and off, then select a location to inspect its reactor-level evidence.
Every coloured circle represents one reactor entry, using the same unit-dot scale as Fleet Geography; mixed-status sites therefore remain mixed-colour. Unit numbers remain visible at rest, while hover, focus or click adds spacing for easier identification. Approximate coordinates over a Natural Earth coastline. Statuses are source-dated and are not presented as live unless explicitly identified as an operator snapshot.
33 is the commercial fleet denominator
Generating, temporarily not confirmed and restart-pipeline statuses are mutually exclusive views of the same 33 existing units.
JAIF fleet source ↗27 is a separate JAIF table
It includes ordinary commercial units, Fukushima Daiichi, two research/development reactors and one completed dismantlement.
JAIF closed-down source ↗Three units, separately classified
Ohma, TEPCO Higashidori 1 and Shimane 3 remain in JAIF's under-construction table; “TBD” is not a forecast.
JAIF construction source ↗Mihama is the strongest current signal
KEPCO is surveying for a successor unit and calls an advanced light-water reactor the realistic option. MHI's SRZ-1200 is a credible candidate, but no design or vendor has been selected.
KEPCO primary source ↗Eight dated plans—not forecasts
JAIF still lists eight planned units. Kaminoseki and Tsuruga preparation is suspended; no listed unit has a construction or operation date.
JAIF planned table ↗