JAPAN POWERWATCHDashboard
JAPAN NUCLEAR · REGULATION

From regulatory documents
to commercial decisions.

Verified NRA developments, reactor review positions and the next observable gate—translated and structured for international companies.

ACTIVE NRA REVIEW4

Existing reactors without conformity approval

APPROVED / ADVANCED3

Still facing construction, inspection or consent gates

REGULATORY BLOCK1

Tsuruga 2 in the current fleet register

RECENT DEVELOPMENTS5

Primary-source records in this first page version

What changed—and why it matters

Facts, interpretation and next gates are kept separate.

APPLICATION WITHDRAWAL

NRA receives the Hamaoka 3 and 4 application withdrawals

The NRA received withdrawal documents for both units' installation-change applications and for Unit 4's construction-plan and operational-safety-rule applications.

Withdrawals received⌄
AFFECTED

Hamaoka 3 · Hamaoka 4 · Chubu Electric

NEXT OBSERVABLE GATE

A new operator decision and new conformity applications would be required before an active regulatory restart pathway can resume.

BUSINESS IMPLICATION

The active review path has ended for both units, increasing restart uncertainty while leaving the units in the 33-reactor existing-fleet denominator.

ORIGINAL RECORD

中部電力(株)から浜岡原子力発電所3号炉及び4号炉の新規制基準適合性に係る発電用原子炉設置変更許可申請等の取下書を受理

NRA / N-ADRES source ↗
REACTOR REVIEW

NRA schedules a non-public safety-facility review for Kashiwazaki-Kariwa 6 and 7

The NRA scheduled a conformity-review meeting covering specific severe-accident response facilities for Units 6 and 7. The meeting is non-public because it concerns protected facility information.

Meeting scheduled⌄
AFFECTED

Kashiwazaki-Kariwa 6 · Kashiwazaki-Kariwa 7 · TEPCO

NEXT OBSERVABLE GATE

Any resulting requests, submissions or regulatory conclusions published after the closed review.

BUSINESS IMPLICATION

The review is relevant to completion risk and sequencing for TEPCO’s restart programme, but the meeting notice alone does not indicate approval or delay.

ORIGINAL RECORD

第1423回原子力発電所の新規制基準適合性に係る審査会合

NRA / N-ADRES source ↗
AGEING MANAGEMENT

Kashiwazaki-Kariwa 6 ageing-management review examines technical evaluations

The meeting considered TEPCO responses and technical material covering ageing mechanisms, instrumentation, concrete and steel structures, and seismic and tsunami safety.

Under review⌄
AFFECTED

Kashiwazaki-Kariwa 6 · TEPCO

NEXT OBSERVABLE GATE

NRA resolution of outstanding review comments and a decision on the long-term facility management plan.

BUSINESS IMPLICATION

The outcome affects the unit’s long-term operating permissions and may drive inspection, replacement and engineering-service requirements.

ORIGINAL RECORD

第33回実用発電用原子炉の長期施設管理計画等に係る審査会合

NRA / N-ADRES source ↗
FUEL CYCLE

Sendai dry-storage proposal advances through technical review

Kyushu Electric presented responses and supplementary conformity material for proposed spent-fuel dry-storage facilities at Sendai.

Responses submitted⌄
AFFECTED

Sendai 1 · Sendai 2 · Kyushu Electric

NEXT OBSERVABLE GATE

NRA confirmation that the design and supporting analysis satisfy the installation-permission requirements.

BUSINESS IMPLICATION

Additional storage capacity can reduce a future fuel-management constraint and creates potential demand across casks, civil works, handling systems and inspection services.

ORIGINAL RECORD

第1419回原子力発電所の新規制基準適合性に係る審査会合

NRA / N-ADRES source ↗
SYSTEM UPDATE

NRA publishes its July national conformity-review snapshot

The NRA updated its plant-by-plant review material, including recent meetings, review status and principal open issues.

Official snapshot⌄
AFFECTED

National fleet

NEXT OBSERVABLE GATE

Monitor reactor-specific hearings and document revisions rather than treating the periodic snapshot as a restart schedule.

BUSINESS IMPLICATION

The document is the common regulatory baseline for comparing review maturity, unresolved technical topics and likely demand for safety-related work.

ORIGINAL RECORD

新規制基準適合性審査の進捗状況等について(発電用原子炉関係)

NRA / N-ADRES source ↗

Units with an active or advanced regulatory pathway

NRA national snapshot ↗
REACTOROPERATORCURRENT POSITIONNEXT GATE
Tomari #3Hokkaido EPCSafety works / detailed approvalsComplete design-and-construction approvals, safety works and pre-use inspections.

NRA installation-change permission granted 30 Jul 2025; Hokkaido governor accepted restart in Dec 2025.

Source snapshot ↗
Tokai #2JAPCApproved / safety constructionComplete construction and obtain the required local-government consent.

NRA conformity approval obtained in 2018; safety measures, including the SSF, scheduled for completion in Dec 2026.

Source snapshot ↗
Kashiwazaki-Kariwa #7TEPCOApproved / strategy resetTEPCO must confirm the unit sequence and secure the remaining restart readiness and local acceptance.

NRA conformity approval obtained in 2017; fuel loading and equipment checks were completed, then fuel removal began in Oct 2025.

Source snapshot ↗
Tomari #1Hokkaido EPCNRA conformity reviewResolve review issues, complete safety works and obtain local acceptance.

Application has been under NRA review since Jul 2013; no conformity approval.

Source snapshot ↗
Tomari #2Hokkaido EPCNRA conformity reviewResolve review issues, complete safety works and obtain local acceptance.

Application has been under NRA review since Jul 2013; no conformity approval.

Source snapshot ↗
Higashidori #1Tohoku EPCNRA conformity reviewComplete the regulatory review and establish a safety-construction schedule.

Application has been under NRA review since Jun 2014; safety-work completion date is undecided.

Source snapshot ↗
Shika #2Hokuriku EPCNRA conformity reviewComplete the regulatory review and address site and safety-work requirements.

Application has been under NRA review since Aug 2014; no conformity approval.

Source snapshot ↗
Tsuruga #2JAPCNot permitted by NRAThe current regulatory outcome must be overcome before a restart pathway can exist.

NRA concluded in Nov 2024 that the reactor did not meet the new regulatory standards.

Source snapshot ↗

Next published regulatory event

Dates appear only after an NRA notice is available.
Emergency Action Level review meeting — reprocessing facilities

Rokkasho reprocessing / emergency preparedness · Official meeting record

Meeting record ↗

Regulatory status is not a restart forecast. Source dates, operator construction schedules and local-government consent remain separate gates.